Hi Experts,
I have created a Process Chain that needs to be triggered off after an Event. Both the Process Chain and Event are loaded on a Daily basis.
I used to run the Process Chain manually until an Event was created recently.
I have changed the Process Chain last friday to trigger off after this Event but I noticed that the Event is not triggering off the Process Chains.
Can anyone let me know what the issue is?
When I looked into the Process Chain in Change mode -> Doubleclick on Start Variant -> Change Selections:
I could notice 'Immediate start' is still checked but greyed out under 'Immediate' tab. Also Event's name is there in 'After Event' tab. Does this make any difference?
FYI - I unchecked 'Periodic job' while changing the Process Chain earlier because I don't want it to run periodically. I want the Process Chain to run only after the Event is finished.
Also, please let me know how to move a Process Chain from 'Not Assigned' to other areas.
Any help in this regard is much appreciated. Points are assigned.