SAP BI 7.4 Project System Implementation issues.

$
0
0

Hi All,

 

Working for Construction Comapany.They are implementing PS --> BW.

 

There are two areas in the reports Project Time line,Cost Estimates

 

Construction Start DatePlanned End DateAct/Forecast End DateDelay (mnths)Total Project Budget (INR Crs)Spend Till Date (INR Crs)Target for the Month (INR Crs)Actual for the Month (INR Crs)Variance %Spend Till Date (INR Crs)Balance (INR Crs)

 

 

Total Project Budget (INR Crs) and Target for the Month (INR Crs) are coming from excel.

 

Can anyone guide me which DataSource used for the rest fields since they have given me some tables through which data is coming.

 

Table names : PROJ,PRTE,BPGE,RPSCO,PRPS.

 

Thanks,

Mayur